| Rule | 16 CFR part 1209Interim Safety Standard for Cellulose Insulation |
|---|---|
| Covers | Cellulose insulation |
| Certificate | General Certificate of Conformity (GCC) |
| Third-party testing | Not required to be third party: a test of each product or a reasonable testing program |
| eFiling citation code | 1209 |
| In force since | October 15, 1979§ 1209.11 |
| CPSC import estimate | 5,764 importers, 46,511 filings a year90 FR 1800, Table 15 |
What the rule covers
16 CFR 1209 applies to cellulose insulation. Its scope provision reads:
This part 1209, an interim consumer product safety standard, prescribes flame resistance and corrosiveness requirements for cellulose insulation that is a consumer product.§ 1209.1(a), eCFR
| Term | Definition in the rule | Section |
|---|---|---|
| Cellulose insulation | Cellulose insulation means cellulosic fiber, loose fill, thermal insulation that is suitable for blowing or pouring applications. | § 1209.2(a) |
| Private labeler | Private labeler means an owner of a brand or trademark which is used on the label of cellulose insulation subject to the standard which bears a private label as defined in section 3(a)(7) of the act (15 U.S.C. 2052(a)(7)). | § 1209.32 |
What the rule requires
| Requirement | Section |
|---|---|
| Insulation must be noncorrosive in the metal coupon test. | § 1209.3(a) |
| Critical radiant flux must be at least 0.12 W/cm² for each of three specimens. | § 1209.3(b) |
| In the smoldering test there may be no flaming and weight loss must be 15% or less. | § 1209.3(c) |
| Bagged insulation is certified by marking each bag with the label statement, issuer name, date and place of manufacture. | § 1209.39(a)(1) |
| Importers must issue the certificate and may rely on foreign test records only if the records are kept in the U.S. | § 1209.39(c) |
The required wording, verbatim:
This product meets the amended CPSC standard for flame resistance and corrosiveness of cellulose insulation.16 CFR part 1209
What is exempt or outside the rule
- When several parties could certify, only the one closest to the consumer must issue the certificate. (§ 1209.40)
Which certificate, and who tests
CPSC's list of rules requiring a General Certificate of Conformity names “Cellulose insulation” (16 CFR part 1209). The eFiling code list of December 18, 2025 marks 1209 as a GCC rule. For general-use products CPSC says a GCC rests on a test of each product or a reasonable testing program, and first-party testing or any qualified lab can support it, so a CPSC-accepted lab is not required.
CPSC's own eFiling burden estimate in the 2025 final rule (90 FR 1800, Table 15) counts 5,764 importers of cellulose insulation filing 46,511 certificates a year, all of them GCCs.
When it took effect
| What | Date | Source |
|---|---|---|
| Standard (including label) applies to insulation manufactured after | October 15, 1979 | § 1209.11 |
| Certification subpart B effective | October 16, 1979 | § 1209.41 |
What goes in the eFiling record
Each entry carries the certificate data in a Full PGA Message Set or as a Reference to a certified record in the CPSC Product Registry, citing code 1209 plus a code for every other rule the product is certified to. See the seven certificate data elements.
Data: this citation is a row in the Import Certs CPSC Certificate Rule Lists 2026.11, free as CSV and JSON under CC BY 4.0.
Common questions
Do imported cellulose insulation need a CPC or a GCC?
A General Certificate of Conformity. CPSC's eFiling code list marks 1209 as a GCC rule, and third-party testing is not required.
What is the CPSC eFiling citation code for 16 CFR 1209?
1209, from CPSC's eFiling citation code list dated December 18, 2025. List it with a code for every other rule the product is certified to.
Can an importer rely on foreign test records for cellulose insulation?
Yes, only if the records are kept in the United States; importers must issue the certificate themselves (16 CFR 1209.39(c)).
- 16 CFR part 1209, PART 1209: INTERIM SAFETY STANDARD FOR CELLULOSE INSULATION (eCFR, current)
- 44 FR 39966, July 6, 1979
- 44 FR 39983, July 6, 1979
- CPSC, Rules Requiring a General Certificate of Conformity
- CPSC eFiling Citation and Testing Exclusion Codes, December 18, 2025 (xlsx)
- 16 CFR part 1110, Certificates of Compliance (eCFR, current)
- CPSC final rule, Certificates of Compliance, 90 FR 1800, January 8, 2025